  • June 2022 News

    31 July 22

    5th floor- :- Piping implementation of sprinklersFloor 1+ to +3:- Implementation of wiring (fan coil system)- Implementation of wiring (mother clock system)- Implementation of audio system wiring4th floor:- Implementation of support, pipe and key box...

  • May 2022 News

    5 July 22

    Negative floors and ground floor:- Implementation of the masonry wall of the 4th floor-- Implementation of EN7 and EN13 elevator wall paint on the ground floor- Implementation of Kenaf EN7 wall color on the ground...

  • April 2022 News

    1 June 22

    Negative and ground floors:- Ceramic execution of floors -4 and -5- Execution of corrugation for the implementation of sewer pipes in the 1st floor- Execution of sewer pipes (area number 1) floor-1- Execution of sprinkler...

  • March 2022 News

    2 May 22

    Negative and ground floors:- Execution of wall paint of elevator EN2 floors -7 to -9- Execution of EN9 elevator wall paint, floors -3 and -4- Execution of EN2 elevator wall paint and implementation of EN5...

  • February 2022 News

    19 April 22

    Negative and ground floors:- Execution of piping sprinklers 5-- Execution of piping sprinklers 4-- Execution of Knauf wall substructure, 4th floor- Execution of leaf plaster on the wall of the first layer of the first...

  • January 2022 News

    1 March 22

    - Negative and ground floors:- Execution of stair treads on floors -1 and -3- Execution of elevator wall post EN10 ground floor- Class +1:- Execution of wiring (electrical system)- Ceramic execution- Execution of flooring of...