February 2021 News
23 April 21- Carrying out operations related to buildings and facilities in +1 to +6 floors- Execution of masonry wall of floors +3 to +6 and floors +17 to 23.- Execution of Knauf wall leaf plaster of...
- Carrying out operations related to buildings and facilities in +1 to +6 floors- Execution of masonry wall of floors +3 to +6 and floors +17 to 23.- Execution of Knauf wall leaf plaster of...
- Carrying out operations related to buildings and facilities in classes +1 to +6- Execution of stone wool and knauf wall of floors 1+ to 5+.- Installation of medical gas ceiling columns on the ground...
- Carrying out operations related to buildings and facilities in +1 to +6 floors- Execution of waterproofing of floors 1+ to 3+ and execution of stone floor of floors +1 to +4- Execution of cementing...
- Operations related to buildings and facilities in the +1 to +6 floors are underway.- The total progress in the +1 and +2 classes is about 90%, which is about 91% in the buildings sector,...
- Operations related to buildings and facilities in the +1 to +5 floors are underway.- The total progress in the +1 and +2 classes is about 77%.- The total progress in the +3 to +5...
- 95% progress in the construction of four engine room chillers by Sari Pouya Company- Concluding a contract with Mehr Fakhr Company to supply and supply 57 elevators with the Otbis China brand.- Preparing and...