1st floor :
- Subframe installation
- Implementation of the infrastructure of the inner Kenaf wall
- Common support installation
Floor +1:
- Implementation of UPS system wiring
2nd floor:
- Implementation of wiring (electrical system)
- Implementation of UPS system wiring
3rd floor:
- Implementation of wiring (lighting system)
- Implementation of UPS system wiring
4th floor:
- Implementation of wiring (lighting system)
- Implementation of wiring (electrical system)
- Implementation of wiring (audio system)
- Implementation of wiring (mother clock system)
6th floor:
- Implementation of wiring (mother clock system)
- Installation of fresh and exhaust air channels
7th floor:
- Performance of stone wool
- Performing mosaics
- Carrying out cabling (summoning a nurse)
- The hardening operation related to the parking lots, clinic and hospital is being implemented and the overall progress has reached about 44%.
- Fine work operations related to parking lots, clinic and hospital are being implemented and the overall progress has reached about 28 percent.