  • June 2025 News

    8 August 25

    • Continue internal gas piping operations and perform pipe welding tests under the supervision of the engineering system supervisor and assign expansion loops• Start fixing defects in the large amphitheater hall and lobby on floor...

  • May 2025 News

    16 July 25

    • Temporary handover of the executive operations of the large amphitheater hall and lobby on floor +1• Installation of low-voltage electrical panels of the engine room and coordination with Lenazd Company for the entry of...

  • April 2025 News

    28 June 25

    • Continuing internal gas piping operations and conducting pipe welding tests under the supervision of the engineering system supervisor• Installing low-pressure electrical panels in the engine room• Planning to start the second compression chiller on...

  • March 2025 News

    10 May 25

    • Execution of executive operations of the large amphitheater hall and lobby on floor +1• Planning for the installation of low-pressure electrical panels in the engine room• Continuing the construction of the project's air conditioners•...

  • February 2025 News

    17 March 25

    • Continuing internal gas piping operations and conducting pipe welding tests under the supervision of the engineering system supervisor• Continuing the implementation of the hospital's amphitheater and assembly halls on the 1st floor (including the...

  • January 2025 News

    15 February 25

    • Continuing internal gas piping operations and conducting pipe welding tests under the supervision of the engineering system supervisor• Planning for the commissioning of low-pressure electrical panels in the engine room• Continuing executive operations on...