August 2026 News

August 2026 News

• Continuing the implementation of the CSR section and the oxygen generator on the 8th floor+
• Continuing the implementation of the ground floor lobby
• Completing the reinforcement, joinery and installation of the additional space to equip the labor camp
• Installing fire alarm and extinguishing equipment on the floors
• Implementing fire and smoke barriers for the ceiling joints and ceramic wall of the gas riser on the floors
• Continuing the construction of the project's air conditioners and delivering 60 units from Rifle Company
• Planning to purchase all the project's control valves
• Planning to purchase fire-resistant doors for the first phase of the project

Floor 1-:
Implementing the staining of the ceiling and walls
Installing air vents
Installing sprinkler nozzles
Installing fire alarm equipment
Installing the electrical panel
Installing the lights

Ground floor:
Implementing the support, tray and electrical piping of the lobby
Starting the operation of the western and southern areas

Floor 1+:
Completing the central zone Knauf ceiling panel
Implementing the central zone floor ceramic
Implementing the foundation and installing the panel False ceiling of the southern zone
Implementing the type and putty and painting of the southern zone
Implementing the fire and smoke barrier of the ceiling seam and electrical and mechanical elements
Implementing the inspection hatch of the southern zone ceiling
Installing the electrical panels of the southern zone
Installing the lights of the southern zone
Installing dry ceramic facade of the ramp on the southeast side
Implementing the gas piping of the eastern ramp
Implementing the sheet and rock wool of the chimney of the diesel generators of the engine room on the southeast side
Implementing the cementing of the eastern ramp wall
Installing the plinth stone of the eastern ramp

Floor 2+:
Installing dry ceramic facade of the ramp on the southeast side
Implementing the brickwork and cementing of the eastern ramp dock
Implementing the fire alarm support and piping of the central zone
Implementing the ceramic floor of the elevator lobby on the north side
Implementing the support and electrical pipes of the southern zone
Implementing the steam lines of the southern zone

Floor 3+:
Implementing the foundation of the riser wall
Implementing the riser smoke barrier
Implementing the lines Towel dryer, toilet and fan coil in the southern management room
Construction, insulation and installation of air conditioning ducts in the southern management room
Implementation of earth bonding cable
Installation of support and piping in the southern and western zones
Implementation of the substructure of the western zone Knauf ceiling
Implementation of ceramic floor in the western zone
Implementation of the ceiling paint in the southern zone air conditioning room

Floor 6+:
Implementation of falsework and full mesh in the central zone
Implementation of cementing the central zone wall
Implementation of ceramic wall in the central zone

Floor 8+:
Implementation of wall tiling, full mesh and cementing in the eastern zone air conditioning room
Implementation of wall tiling and soundproofing of the CSR section wall in the eastern zone
Implementation of full mesh and cementing of the CSR section in the eastern zone
Implementation of falsework in the CSR section in the eastern zone
Implementation of support and sewage piping in the CSR section in the eastern zone

Floor 9+:
Implementation of construction, insulation and installation of air conditioning ducts in the eastern and western zones
Implementation of support for air conditioning ducts in the western zone
Full welding of the lines implemented
Implementation of medical gas lines for risers
Construction and placement of the air conditioner chassis in the western zone

Floor 17+:
Implementation of the ceiling painting operation in the western zone
Implementation of the ceiling panel in the western zone wet area
Installation of the air conditioning vents in the western zone

Floor 26+:
Implementation of the piping of the cooling and heating system in the engine room
Construction and implementation of the chassis and installation of the ground and linear pumps in the engine room
Installation of the valves in the cooling and heating system in the engine room
Construction and installation of the collectors in the engine room
Implementation of the supports and pipes in the central zone