May 2022 News
5 July 22Negative floors and ground floor:- Implementation of the masonry wall of the 4th floor-- Implementation of EN7 and EN13 elevator wall paint on the ground floor- Implementation of Kenaf EN7 wall color on the ground...
Negative floors and ground floor:- Implementation of the masonry wall of the 4th floor-- Implementation of EN7 and EN13 elevator wall paint on the ground floor- Implementation of Kenaf EN7 wall color on the ground...
Negative and ground floors:- Ceramic execution of floors -4 and -5- Execution of corrugation for the implementation of sewer pipes in the 1st floor- Execution of sewer pipes (area number 1) floor-1- Execution of sprinkler...
Negative and ground floors:- Execution of wall paint of elevator EN2 floors -7 to -9- Execution of EN9 elevator wall paint, floors -3 and -4- Execution of EN2 elevator wall paint and implementation of EN5...
Negative and ground floors:- Execution of piping sprinklers 5-- Execution of piping sprinklers 4-- Execution of Knauf wall substructure, 4th floor- Execution of leaf plaster on the wall of the first layer of the first...
- Negative and ground floors:- Execution of stair treads on floors -1 and -3- Execution of elevator wall post EN10 ground floor- Class +1:- Execution of wiring (electrical system)- Ceramic execution- Execution of flooring of...
- Floor +2:- Implementation of waterproofing- Apply floor protective mortar- Ceramic execution- Execution of cabling (power supply of electrical panels from the floor)- Wiring implementation (lighting system)- Execution of wiring (electrical system)- Floor +3:- Execution...