2nd Floor- :
- Implementation of sewer pipes
- Installation of cooling system valves
- Construction of electric motor chassis
- Construction of the knee of the steam system
Floor 3+:
- Implementation of elastomeric insulation of the water supply system (galvanized pipe)
- Implementation of elastometric insulation of steel pipe
Floor 6+:
- Implementation of elastomeric insulation of fresh and outgoing air channels
- Construction of fresh air ducts and transportation to the installation workshop
- Installation of fresh and exhaust air channels
Floor 18+:
- Installation of sanitary ware in A10 offices
- Installation of office lights B1 to B10
- Installation of office lights C1 to C10
- Installation of lights for offices A1 to A9
- Installation of the corridor light in the southern zone
- Installation of switches and sockets in the office B1 to B10
- Installation of switches and sockets in the office C1 to C9
- Installation of switches and sockets for offices A1 to A10
- Installing the switch, outlet in the corridor of the southern, eastern and western zones
- Installation of switches and sockets for the services of the corridor in the south-eastern zone
- Installation of service lights in the corridors of the southern and western zones of the east
- Installation of switches and sockets for corridor services in the western and eastern zones
- Installation of corridor lights in the west zone
Floor 19+:
- Implementation of electric pipe under the roof of dry spaces of offices A1, A2, A3
- Implementation of electric pipe in the wet space of office B3
- Wiring and installation of switches and sockets in the office B1 to B10
- Wiring and installation of the key and socket of the office C1 to C10
- Wiring and brain installation of offices A1 to A10
- Implementation of electric pipe in the corridor of the western and eastern zones
- Implementation of electrical wiring in the corridor of the western and eastern zones
- Implementation of the electric pipe of the corridor services in the western zone
- Installation of support and implementation of sprinkler piping in the southern zone
- Installation of eastern zone channels
Floor 20+:
- Installation of channels in the western zone
- Implementation of sewage piping in the western zone
- Installation of support and implementation of sprinkler piping in the western zone
- Implementation of the piping of the fan coil in the western zone
- Implementation of the electric pipe in the corridor of the western zone
- Installation of South Zone channels
- Installation of support and implementation of sprinkler piping in the southern zone
- Piping implementation of the southern fan coil zone
- Implementation of the electricity pipe of the South Zone Corridor
- Installation of eastern zone channels
- Installation of support and implementation of sprinkler piping in the eastern zone
- Installation of support and implementation of piping for the eastern fan coil zone
- Implementation of the electric pipe in the corridor of the eastern zone
- The physical progress of the whole project is 74.07%.
- The hardening operation related to the parking lots, clinic and hospital is being implemented and the overall progress has reached about 54%.
- Fine work operations related to parking lots, clinic and hospital are being implemented and the overall progress has reached about 41 percent.