2nd Floor- :
- Installing the flange and gasket of the cooling and heating system
- Implementation of cooling system pipelines on supports
- Construction and installation of heating system piping saddles
- Installation of steam system flange and gasket
- Construction and installation of steam system piping saddles
- Implementation of steam system pipelines on supports
- Construction and installation of soft water system piping saddles
- Installing the flange and gasket of the water supply system
- Construction and installation of saddles for water supply system piping
- Construction of saddles under the fire system piping
- Construction of heating and water supply knee
Floor 4+:
- Implementation of waterproofing
- Implementation of floor protective mortar
- Implementation of leaf plaster of Kenaf wall of the first layer of the second face of MR
- Implementation of elastometric insulation of steel pipe
Floor 5+:
- Wet space flooring
- Implementation of wiring (Priserbuk system)
Floor 7+:
- Implementation of waterproofing
- Implementation of floor protective mortar
- Wet space flooring
- Subframe installation
- Rock wool
- Implementation of body ceramics
- Implementation of elastomeric insulation of fresh and outgoing air channels
- Implementation of pipes and cans of switches and sockets
- Implementation of wiring (lighting system)
- Implementation of wiring (Prisbarg system)
- Construction of fresh air ducts and transportation to the installation workshop
- Construction of return and discharge air channels and transportation to the workshop
- Installation of return and exhaust air channels
- Construction of channel risers and positive pressure of stairs
- Installation of channel risers and positive pressure of the staircase
- Implementation of elastomeric insulation of the water supply system (galvanized pipe)
- Implementation of fire system piping (firebox piping)
- The physical progress of the whole project is 73.45%.
- The implementation of facilities related to parking lots, clinic and hospital is being implemented and the overall progress has reached about 49%.
- The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached a total progress of 54%.
- The implementation of electrical facilities related to parking lots, clinics and hospitals has reached a total progress of 44%.