December 2020 News
25 January 21- Carrying out operations related to buildings and facilities in +1 to +6 floors- Execution of waterproofing of floors 1+ to 3+ and execution of stone floor of floors +1 to +4- Execution of cementing...
- Carrying out operations related to buildings and facilities in +1 to +6 floors- Execution of waterproofing of floors 1+ to 3+ and execution of stone floor of floors +1 to +4- Execution of cementing...
- Operations related to buildings and facilities in the +1 to +6 floors are underway.- The total progress in the +1 and +2 classes is about 90%, which is about 91% in the buildings sector,...
- Operations related to buildings and facilities in the +1 to +5 floors are underway.- The total progress in the +1 and +2 classes is about 77%.- The total progress in the +3 to +5...
- 95% progress in the construction of four engine room chillers by Sari Pouya Company- Concluding a contract with Mehr Fakhr Company to supply and supply 57 elevators with the Otbis China brand.- Preparing and...
- Execution of 400 units in the facade equivalent to 2000 square meters- Execution of operations of buildings and facilities in floors +1 to +5- Holding HSE meetings- Holding weekly and continuous meetings with contractors-...
- Organizing engineering meetings virtually to review plans- Pursuing the supply of electricity to the project through the supply contractor and requesting to prepare final supply plans for the project- Following up with the official...