May 2021 News
2 July 21- Floors +1 to +4Execution of valve of medical gas system, cement facade of +1 floorExecution of fan coil, installation of support and execution of fresh and departure air ducts, construction of return air ducts...
- Floors +1 to +4Execution of valve of medical gas system, cement facade of +1 floorExecution of fan coil, installation of support and execution of fresh and departure air ducts, construction of return air ducts...
- Execution of wiring (lighting system), execution of floor coil +1- Execution of elastomeric insulation of fresh air duct and +3, implementation of wiring (fire alarm system), implementation of wall cementing, implementation of wall cementing...
- Execution of elastomeric insulation of water supply system of +4 floor and execution of fan coil of +3 and +4 floors.-Support bricks, pipes and key boxes of +4 and +5 floors and execution of...
- Carrying out operations related to buildings and facilities in +1 to +6 floors- Execution of masonry wall of floors +3 to +6 and floors +17 to 23.- Execution of Knauf wall leaf plaster of...
- Carrying out operations related to buildings and facilities in classes +1 to +6- Execution of stone wool and knauf wall of floors 1+ to 5+.- Installation of medical gas ceiling columns on the ground...
- Carrying out operations related to buildings and facilities in +1 to +6 floors- Execution of waterproofing of floors 1+ to 3+ and execution of stone floor of floors +1 to +4- Execution of cementing...