February 2022 News

19 April 22 Print

February 2022 News

February 2022 News

Negative and ground floors:
- Execution of piping sprinklers 5-
- Execution of piping sprinklers 4-
- Execution of Knauf wall substructure, 4th floor
- Execution of leaf plaster on the wall of the first layer of the first face of Knauf, 4th floor
- Destruction of 4th floor ceramics
- Execution of 4th floor ceramics
- Installation of 4th floor subframe
- Execution of Valkyrit mesh and glue, white cement, wall paint, flooring, floor mosaic, Valkyrit wall, Valkyrit mesh and adhesive, white cement, electrical room wall paint, 8th floor
- Execution of elevator wall paint on floors 1- to 4- and 8-
- Execution of mesh and glue, white cement, wall paint, flooring, floor mosaic, wall and wall, electric room, 5th floor
- Execution of Knauf wall substructure installation, execution of Knauf wall installation EN1, EN3, EN4 ground floor

Floor +2:
- Execution of plaster on the wall of the second layer of the first layer of FR + 2
- Ceramic execution
- Execution of mosaic
- Execution of cabling (power supply of electrical panels from the floor)
- Wiring (UPS + 2 system)
- Execution of wiring (electrical system)
- Execution of cabling (fire alarm system or cable detector)

Floor +3:
- Ceramic execution
- Execution of rock wool
- Execution of wiring (electrical system)

Floor +5:
- Execution of rock wool
- Wiring implementation (lighting system)
- Execution of EN12 elevator valcrete


Floor +18:
- Execution of ceramic bodies of A4 to A7 offices
- Implementing waterproofing of wet spaces of A9 and A10 offices
- Execution of protective layer of waterproofing of wet spaces of A7 to A10 offices
- Cementing of wet spaces of A1 to A5 offices
- Plastering of C6 to C8 offices
- Execution of electrical pipes on the walls of dry spaces of offices A1, A2, A3
- Grooving on the walls of uncoated (dry) spaces of offices A1, A2, A3
- Execution of western zone fan coil piping
- Construction and installation of western zone canals
- Installation of support and execution of sprinkler piping in the east, west and south zones
- Execution of sewage piping of east and west corridor services
- Testing hot and cold water piping for wet spaces of offices A1, A2, A3
- Execution of hot and cold water piping for wet spaces of offices C1, C2, C3
- Execution of wet space sewage piping in C6 and B6 offices
- Execution of hot and cold water piping for wet space in C10 office
- Execution of electricity pipes in the western zone corridor
- Execution of electrical pipes under the roof of dry and wet spaces of A5 offices
- Execution of flooring and installation of flooring in the corridor services of the western zone
- Installation of wall posts, plastering and execution of wall walls of C1, C2, C3 offices
- Flooring of wet spaces of A1 to A10 offices

- Implementation of facilities related to parking lots, clinics and hospitals is underway and the overall progress has reached about 32%.
- Implementation of mechanical facilities related to parking lots, clinics and hospitals to progress
The total has reached 37%.
- Implementation of electrical installations related to parking lots, clinics and hospitals in progress
The total has reached 29 percent.