March 2022 News

2 May 22 Print

March 2022 News

March 2022 News

Negative and ground floors:
- Execution of wall paint of elevator EN2 floors -7 to -9
- Execution of EN9 elevator wall paint, floors -3 and -4
- Execution of EN2 elevator wall paint and implementation of EN5 elevator wallcrete, 7th floor
- Execution of elevator wall post EN7 floor -3
- Execution of elevator valcrete EN10 floor -2
- Execution of wall paint of elevator EN2 Execution of wall post of elevator EN7 ground floor

Floor +1:
- Execution of installation of Knauf wall infrastructure EN3, En4 and En7
- Wiring implementation (lighting system)
- Execution of wiring (electrical system)
- Execution of UPS + 1 wiring
- Ceramic execution
- Execution of rock wool

Floor +2:
- Execute the wall paint of the elevator EN1
- Execution of elevator wall post EN13, EN7
- Execution of installation of Knauf EN7 wall substructure
- Execution of Knauf EN7 wall installation
- Apply floor protective mortar

Floor +3:
- Execute the wall paint of the elevator EN1
- Execution of elevator wall post EN13, EN7
- Execution of installation of Knauf EN7 wall substructure
- Execution of Knauf EN7 wall installation
- Implementation of waterproofing
- Apply floor protective mortar

Floor +4:
- Execute the wall paint of the elevator EN1
- Execution of EN7 elevator wall post
- Execution of installation of Knauf EN7 wall substructure
- Execution of wiring (electrical system)
- Wiring implementation (lighting system)
- Apply floor protective mortar

Floor +6:
- Execute the wall paint of the elevator EN1
- Execution of EN7 elevator wall post
- Installation of return and evacuation air ducts

Floor +8:
- Execution of elevator wall post, implementation of elevator wallcrete EN5
- Execution of EN7 elevator wall post
- Execution of the elevator wall post EN14

Floor +17:
- Execute the wall paint of the elevator EN1
- Execution of EN16 elevator knauf wall installation
- Execution of elevator valcrete and execution of EN17 elevator knauf wall substructure
- Execution of installation of Knauf EN3 wall substructure

Floor +18:
- Execution of electric pipe on the dry space wall of B8 office
- Grooving on the wall of the space without lining (dry) office B8
- Install switch and socket B8
- Execution of EN16 elevator wall paint
- Execution of EN17 elevator wallcrete
- Execution of installation of Knauf EN3 wall substructure
- Execution of elevator wall post and implementation of elevator wallcrete EN5, EN6, EN7

Class +19:
- Execution of EN16 elevator knauf wall substructure
- Execution of EN17 elevator wallcrete


- The physical progress of the whole project is 66%.
- Hardening operations related to parking lots, clinics and hospitals are underway and the overall progress has been about 41%.
- Joinery operations related to parking lots, clinics and hospitals are underway and the overall progress has been about 26%.