November 2021 News

28 December 21 Print

November 2021 News

November 2021 News

-1st floor :
     - Ceramic execution

-floor 4 :
     - Execution of support, pipes and cans of switches and sockets
     - Execution of Knauf wall

8th floor and above:
     - Run the elevator valcrete
     - Execution of rock wool around the knauf wall +14
     - Execution of perimeter knauf wall substructure +15
     - Execution of mesh and adhesive wallcrete for east electric room +18
     - Execution of wallcrete wall of eastern electrical room +18
      - Execution of white cement in the eastern electrical room +18
         
- Implementation of facilities related to parking lots, clinics and hospitals is underway and the overall progress has reached about 27%.
- The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached an overall progress of 30%.
- The implementation of electrical installations related to parking lots, clinics and hospitals has reached an overall progress of 24%.
- Hardening operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 35%.
- Joinery operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 21 percent.