-1st floor :
- Ceramic execution
-floor 4 :
- Execution of support, pipes and cans of switches and sockets
- Execution of Knauf wall
8th floor and above:
- Run the elevator valcrete
- Execution of rock wool around the knauf wall +14
- Execution of perimeter knauf wall substructure +15
- Execution of mesh and adhesive wallcrete for east electric room +18
- Execution of wallcrete wall of eastern electrical room +18
- Execution of white cement in the eastern electrical room +18
- Implementation of facilities related to parking lots, clinics and hospitals is underway and the overall progress has reached about 27%.
- The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached an overall progress of 30%.
- The implementation of electrical installations related to parking lots, clinics and hospitals has reached an overall progress of 24%.
- Hardening operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 35%.
- Joinery operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 21 percent.