August 2023 News

2 October 23 Print

August 2023 News

August 2023 News

9th floor:
- Implementation of water supply system piping (galvanized pipe)
- Implementation of steel piping
- Implementation of pipes and cans of switches and sockets
- Installation of return and exhaust air channels
- Implementation of waterproofing
- Implementation of floor protective mortar
- Implementation of west side mosaic
- Implementation of waterproofing primer
- Implementation of mosaic stringing
- Implementation of braces and installation support
- Installation of manual dampers and return channel fire
- Installation of manual dampers and fire ducts
- Implementation of elastomeric insulation of the water supply system (galvanized pipe)
- Implementation of the sprinkler system pipe
- Water supply system test
- Implementation of flooring operations in dry spaces
- Flooring of wet spaces
- Implementation of elastometric insulation of steel pipe
- Implementation of cable tray
- Firefighting system testing (piping of fireboxes)
- Implementation of floor primer


5th floor-:
- Floor painting


1st floor-:
- Construction of fresh air ducts and transportation to the installation workshop
- Installation of fresh and exhaust air channels
- Construction of evacuation air channels and transportation to the workshop
- Installation of return and exhaust air channels
- Implementation of the sprinkler system pipe
- Installation of manual dampers and return channel fire
- Installation of manual dampers and fire ducts
- Implementation of pipes and cans of switches and sockets
- Implementation of water supply system piping (galvanized pipe)
- Implementation of steel piping
- Implementation of elastomeric insulation of fresh and outgoing air channels
- Implementation of elastomeric insulation of the 5-layer pipe system


Floor 4+:
- Implementation of plaster of Kenaf wall of the first layer of the second face of FR
- Implementation of leaf plaster of Kenaf wall of the first layer of the second face of FM
- Implementation of the foundation of the Kenaf wall
- Implementation of leaf plaster of Kenaf wall of the first layer of the second face of RG
- Implementation of wiring (lighting system)
- Implementation of wiring (electrical outlet system)
- Implementation of leaf plaster of the Kenaf wall of the second layer of the first face of MR
- Installation of manual dampers and fire ducts
- Installation of manual dampers and return channel fire


Floor 5+:
- Carrying out cabling (powering electrical panels from the floor)
- Implementation of the foundation of the Kenaf wall
- Implementation of wiring (lighting system)
- Implementation of wiring (electrical system)
- Implementation of UPS system wiring
- Installation of manual dampers and fire ducts
- Installation of manual dampers and return channel fire
- Implementation of the foundation of the surrounding Kenaf wall
-    Rock wool


Floor 6+:
- Carrying out cabling (supplying electrical panels)
- Implementation of wiring (lighting system)
- Implementation of wiring (Prisbarg system)
- Implementation of cabling (fire alarm system)
- Installation of return and exhaust air channels
- A plastering of the first layer of the Kenaf wall, the second face of RG
- Implementation of plaster of Kenaf wall of the first layer of the second face of FR
- Implementation of leaf plaster of Kenaf wall of the first layer of the second face of FM
- Implementation of wiring (UPS system)
-    Rock wool


Floor 21+:
- Implementation of sewage piping
- Implementation of sprinkler piping
- Implementation of fan coil piping
- Implementation of galvanized piping
- Water supply test
-    Plastering
- Implementation of 5-layer piping

Floor 22+:
- Wall painting and installation of horizontal wallpaper
- Implementation of sewage

 


- The physical progress of the whole project is 75.38%.
- The implementation of facilities related to parking lots, clinics and hospitals is being implemented and has reached a total progress of about 52%.
- Implementation of mechanical facilities related to parking lots, clinic and hospital has reached a total progress of 58%.
- The implementation of electrical facilities related to parking lots, clinics and hospitals has reached a total progress of 47%.