May 2023 News

11 July 23 Print

May 2023 News

May 2023 News

floor -4 :
- Flooring (epoxy floor)
- Implementation of utility duct wall
- Mineral implementation of the northern staircase
- Painting the floor traffic path
- Implementation of epoxy heels of the columns
- Execution of epoxies
- Installation of floor lights
- Implementation of the installation box for stairwell cameras
- Implementation of the wall of the elevator doors
- Implementation of ceramics in front of the elevator door
- Painting the fence for the northern staircase
   
floor -3:
- Execution of the south ramp floor mesh
- Implementation of grinding of the northern ramp
- Implementation of concreting of the southern ramp
- Implementation of the propeller trowel for concreting the south ramp
- South ramp curing implementation
- Implementation of the installation box for stairwell cameras
- Implementation of the wall of the elevator doors
- Painting the fence for the northern staircase


Ground Floor:
- Implementation of the sewage collection pipeline
- Ground floor of the first phase of operation:
- Repairing the wall in front of the elevator door
- Installation of air conditioner
- Implementation of the separating wall of the project
- Implementation of false ceiling chassis
- Implementation of false ceiling
- Installation of the fire door of the northern staircase
- Implementation of the wall of the elevator doors
- The implementation of gas-medical pipeline Riser No. 6
- Painting the fence for the northern staircase
- Implementation of the installation box for stairwell cameras
- Installation of the head board at the entrance 4
   
Floor 2+ and +3:
- Implementation of fire and smoke barriers
- The implementation of gas-medical pipeline Riser No. 6
- Implementation of the installation box for stairwell cameras
- Painting the fence for the northern staircase
 
Floor +17:
- Implementation of electric tray
- Implementation of electrical piping
- Firebox plumbing test
-     Plastering
- Flooring of dry space
- Wet space flooring
- Implementation of the sleeping floor
- Wiring and installation of switches and sockets
- Implementation of the installation box for stairwell cameras
- Painting the fence for the northern staircase
   
Floor +22 to +26:
- Substructure and implementation of mineral stair wall
- Roof bituminous waterproofing
- Protective mortar
- Implementation of slope of roof gutters
- Performing mosaics
- Implementation of wall flushing
- Implementation of plinth stone
- Collection of pool mechanical facilities


- The physical progress of the whole project is 74.60%.
- Rigid operations related to parking lots, clinics and hospitals are being implemented
and has reached a total progress of about 56%.
- Fine work operations related to parking lots, clinics and hospitals are being implemented
and has reached a total progress of about 41 percent.