2nd Floor-:
- Implementation of epoxy substructure of engine room wall
- Implementation of resin and epoxy wall
- Piping of the soft water system of the motor house loop
- Implementation of the piping of the loop water supply system of the motor house
- Installation of piping saddles for the soft water system of the motor house loop
- Installation of piping saddles for the loop water supply system of the motor house
- Construction of air separator chassis (AIR SEPARATOR)
- Installation of heating system flange and gasket
- Installation of strainer and vibration absorber of the heating system
- Installation of heating system valves
- Making saddles for heating system piping
- Installation of saddles under the heating system piping
Floor 7+:
- Implementation of body ceramics
- Implementation of the foundation of the Kenaf wall risers
- Implementation of leaf plaster of the Kenaf wall of the first layer of the first face of MR of the interior space
- Implementation of pipes and cans of switches and sockets
- Implementation of cable tray
- Implementation of wiring (lighting system)
- Implementation of wiring (Prisbarg system)
- Implementation of wiring (fan coil system)
- Implementation of wiring (audio system)
- Implementation of wiring (mother clock system)
- Carrying out cabling (supplying electrical panels)
- Implementation of cabling (network system)
- Fan coil installation
- Implementation of cabling (fire alarm system)
Floor 18+:
- Ceramic restoration
- Fixing the defects of the doors and completing the cornices
Floor 19+:
- Implementation of ceramic floors in dry and wet spaces
- Ceiling painting
- Corridor ceiling painting
- Painting the walls
- Implementation of the ceiling panel of the corridors
- Implementing the roof panel of public services
- Installation of doors
- Fixing electrical piping defects
- Implementation of wiring
- Completing the installation of fan coils
- Installation of lights
- Installation of duct splits
Floor 20+:
- Wet space cementing
- Implementation of false ceiling chassis
- Wet space body ceramic
- Corridor body ceramic
- Repair and completion of electric pipe
- Wiring
- Modifications of sprinkler lines
- Fixing the defects of water supply lines
- Sprinkler test
- Fixing plumbing and electrical wiring defects
- Implementation of cabling
- Installation of support duct splits
The physical progress of the whole project is 75.14%.
The hardening operation related to the parking lots, clinic and hospital is being implemented and the overall progress has reached about 57%.
The delicate operations related to the parking lots, clinic and hospital are being implemented and have reached a total progress of about 41 percent.