2nd Floor-:
Installation of cooling system valves
Construction of cooling system collector
Installation of water supply system valves
Initial installation of piping supports for the water supply system
Construction of water supply system collector
Implementation of sewage pipeline supports
Installation of cooling system flange and gasket
Installation of strainer and shock absorber of the cooling system
Implementation of sewer pipes
Ground floor:
Implementation of the infrastructure of the false ceiling of the pharmacy
Implementation of the false ceiling panel of the pharmacy
Implementation of pharmacy service insulation
Implementation of pharmacy service floor primer
Implementation of brick-laying of the ground floor rainwater well trench
Floor 1+:
Restoration of ceramics
Floor 3+:
Implementation of fire barriers and smoke barriers
Floor 7+:
Rock wool
Implementation of wiring (lighting system)
Implementation of wiring (mother clock system)
Implementation of cabling (fire alarm system)
Cabling implementation (supplying electrical panels)
Installation of manual dampers and fire channel went
Implementation of wiring (pressurized system)
Installation of manual dampers and return channel fire
Implementation of the service floor primer
Insulation of the service floor
Fan coil installation
Run the SFTP cable
Floor 8+:
Implementation of the wall of the workshop
Implementation of the workshop equipment mosaic
Floor 20+:
Implementation of ceramic corridor body
Implementation of ceramic floors in offices
Implementation of ceramic floor services
Plaster implementation
Access corridor cementing
Implementation of false ceiling chassis for dry spaces in offices
Implementation of corridor electrical wiring
Installation of lights, switches, sockets and channel valves for corridor services
Wiring and brain installation of switches and sockets in offices
Implementation of ceramic floors in dry areas of offices
Implementation of air channels
The physical progress of the whole project is 75.47%.
The implementation of facilities related to parking lots, clinic and hospital is being implemented and the overall progress has reached about 52%.
The hardening operation related to the parking lots, clinic and hospital is being implemented and the overall progress has reached about 60%.
The delicate operations related to the parking lots, clinic and hospital are being implemented and the overall progress has reached about 42 percent.