October 2023 News

14 December 23 Print

October 2023 News

October 2023 News

Facade:
Implementation of flushing of the unitized facade of the 16th floor+
Implementation of the plan to strengthen the louvres of the 26th floor
Implementation of sealing of the ground floor
            
Floor -9:
Implementation of valves for the medical gas system
Implementation of medical gas system valve box
Implementation of medical gas system pipe
Implementation of pipes and cans, switches and sockets
Installation of return and exhaust air channels
Installation of fresh and exhaust air ducts

Floor -1:
Implementation of sewer pipes
Implementation of elastomeric insulation of the 5-layer pipe system
Implementation of water supply system piping (galvanized pipe)
Implementation of piping system of 5-layer pipes
Implementation of steel piping
Installation of return and exhaust air channels
  Implementing the sprinkler system pipe
Implementation of pipes and cans, switches and sockets
Implementation of stone wool on the inner wall
Implementation of leaf plaster on the second side of the interior wall
Implementation of installation supports
Implementation of Kargiri
Implementation of insulation of air ducts
Implementation of fan coil channels
Implementation of the towel dryer pipeline
Implementation of elastomeric insulation of the water supply system (galvanized pipe)

Ground floor:
Digging a rainwater well

Floor +6:
Implementation of dock slope concrete
Implementation of ceramics and ceramic banding
Implementation of fire barriers and smoke barriers
Implementation of wiring (UPS system)
    Implementation of wiring (lighting system)
Implementation of wiring (fan coil system)
Implementation of wiring (electrical outlet system)
Implementation of dock primer
Implementation of waterproofing of the dock
Implementation of medical gas riser lock
Implementation of connection channels to the fan coil
Construction of connecting channels to the fan coil
Implementation of cabling (fire alarm system)
           
Floor +16:
Implementation of fire barriers and smoke barriers
Execution of sewage
        
Floor +18:
Installation of wallpaper and Chinese wall on the central side
        
Floor +19:
Install Firefox
Implementation of the sprinkler pipeline
coloring
Central zone plumbing
Implementation of cornices
Installation of doors
Installing the fan coil connection channel
Implementation of fire hose in the central zone
Central zone support
Installing the channel connection to the split duct
Installing office lights
Installation of corridor lights
Installation of key, corridor socket
Installation of corridor service lights
Linear light installation
Installation of office switches and sockets
    
Floor +21:
Implementation of wall cementing
plumbing
Implementation of cable tray
Implementation of sewage
Implementation of pipe insulation
Implementation of the foundation of the Kenaf roof
Implementation of canning
support woman
Implementation of false ceiling chassis for dry spaces of offices
Chimney around the pipe
Implementation of electric pipe under the roof of the dry space of the offices
Installation of split duct chassis
The implementation of electric pipes in wet areas of offices
    
Floor +24:
Install the wallpaper
Implementation of sewage piping
Installation of positive pressure channel
Chinese wall
welding
implementation of chimney
forgery

Floor +25:
Installation of positive pressure channel

Roof:
Implementation of roof wall cementing


The physical progress of the whole project is 75.77%.
The implementation of facilities related to parking lots, clinic and hospital is being implemented and the overall progress has reached about 53%.
The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached a total progress of 60%.
The implementation of electrical facilities related to parking lots, clinics and hospitals has reached a total progress of 47%.