July 2024 News

1 September 24 Print

July 2024 News

July 2024 News

• Continuation of internal gas piping operations, holding meetings with the supervisor of the gas engineering system and obtaining the desired implementation details
• Continue installation of lighting panels by Payasazeh company
• Handing over and resuming the sound insulation of air conditioning rooms
• Continuing the installation of cooling system faucets (to set up cooling towers)
• Continue installing roof cooling towers
• Entry of electrical panels of roof chillers to the workshop
• Implementation of prerequisites for setting up one of the rooftop compression chillers
• Receiving the implementation schedule of the beds (including floors 10-11 and 13)
• Continue the construction of project air conditioners
• Arrival of all phase III elevators (28 machines) to Bandar Abbas customs and a meeting with the supplier to speed up the delivery of the equipment to the workshop.
• Implementation of the foundation of fire pumps on the 2nd floor.
• Complete disassembly of 25 ton tower crane
• Carrying out fine work operations of the transformer rooms on the 2nd floor.
• Continuation of the operation to remove the defects of the 19+ and 20+ floors
• Dismantling the equipment of the workshop on the 17th+ floor (Yal C)
• Continuation of assembling operations of escalators in the manufacturer's factory and coordination for installation in the workshop
• Continue to complete the engine room with the priority of electrical operations
• Preparation of tender documents for electrical panels of Phase I floors
• Purchase of 24 steam milking machines related to engine room absorption chillers
• Continue testing 1 absorption chiller in the engine room and finish strengthening its cover
• Continuation of the operation of the helipad view

1st floor:
Implementation of cabling and bracing and full welding of the sprinkler pipeline
Implementation of the electric pipe and its support and implementation of the lighting system

Floor 1+:
Demolition for Raz Co

Floor 9+:
Implementation of floor opening and buried chassis mesh and floor insulation

Floor 10+:
Implementation of infrastructure and wall panels of Kenaf
Implementation of ceiling column and construction of air ducts and connection of earth and concrete and sewage pipeline
Implementation of electric pipe and support

Floor 11+:
Implementation of Art's connection

Floor 17+:
Implementation of wall painting and lamp installation (south side)
Implementation of fire piping (west side)

Floor 20+:
Implementation of central side flooring

Floor 21+:
Painting the ceiling of offices
Implementation of central side flooring

Floor 22+:
Implementation of false ceiling panel and ceramic floor
Implementation of cabling and wiring
Implementation of central side flooring

Floor 23+:
Implementation of wall and ceiling electric pipes
Implementation of plastering and false ceiling chassis
Implementation of central side flooring

Floor 24+:
Implementation of flooring and plastering
Implementation of wall electric pipe

Floor 25+:
Installation of sleeping floor and execution of ceramic floor in dry space
Implementation of public service sewage piping

Roof:
Modifying and completing facade substructure, cutting work, execution of facade substructure, installation of facade composites, collection of 25 ton tower

The physical progress of the whole project is 78.85%.
The implementation of the facilities has reached a total progress of about 65%.
The implementation of mechanical and electrical facilities has reached a total progress of 68 and 62 percent, respectively.