January 2024 News

13 March 24 Print

January 2024 News

January 2024 News

• Implementation of gas piping, including excavation, restoration and asphalting of the road from the main gas station to the door of the project
• Purchase of electrical panels for the project's facade lighting system
• Notification of the contract for the implementation of the amphitheater and meeting halls of the hospital on the 1st floor
• Notification of the purchase contract for 10 water booster pumps
• Conclusion of the contract for the purchase of all the low pressure panels of the engine room
• Purchase of two garbage disposal machines
• Introduction of sound insulation of air conditioning rooms
• Purchase of all steam valves for the engine room and electric valves for the chiller system
• Start installing compression chillers and roof cooling towers
• Test inspection by one of the inspection companies related to phase 3 equipment of elevators
• Notification of the contract for floors 9-10-11-13
• Notification of the 6th floor contract
• Entry of about 20 air conditioners into the project
 
9th floor-:
Repair and completion of electrical piping and supports

5th floor-:
False ceiling chassis
Implementation of false ceiling panel

2nd Floor-:
Implementation of engine room supports
Piping implementation of the engine room heating system
Installation of intermediate equipment
Implementation of the cooling system pipeline
Implementation of soft water system pipelines
Making double studs to implement support
Implementation of sewage pipeline supports

Floor +5:
Implementation of ceiling column and substructure of laminar flow
Repairing and completing the Kenaf wall

Floor +7:
Implementation of electrical pipes and wiring
Construction of the connecting channel to the fan coil duct on the south side
Installing the connection channel to the fan coil duct on the south side
Flexible implementation of the lighting system
Repairing and completing the Kenaf wall
Implementation of wet space insulation
Modifying and completing the network system

Floor +19:
Installation of internal door frames
Implementation of central zone sewage

Floor +20:
Installation of switch and socket on the south side
South and east side wall painting
Installation of the cornice of the office on the east side
Installation of internal doors on the east side
Installation of ceiling electric pipe and walls of wet space in the central zone
Installation of lights in the eastern zone

Floor +22:
Implementation of the ceiling electric pipe of the corridor on the west side
The chassis of the false roof of the dry space on the west side
Cementing the corridor on the east side

Floor +23:
Installation of common support for the south corridor
Installation of sprinkler pipe and galvanized pipe on the east side

Floor +25:
Installation of wall-post and perimeter wall-crete on the east side
 
The physical progress of the whole project is 77.9%.
The hardening operation related to the parking lots, clinic and hospital is being implemented and the overall progress has reached about 64%.
The delicate operations related to the parking lots, clinic and hospital are being implemented and the overall progress has reached about 47 percent.