Negative classes:
- Execution of the epoxy initial layer of the outer wall of the eastern staircase of the 2nd floor
- Destruction of wastewater treatment floor, floor -2 to change the position of sewage pumping
- Reinforcement of elevator shaft EN2.9 for concreting the floor of the elevator area
- Execution of reinforcement of the north ramp pads of the 3rd floor to the ground floor for concreting
- Demolition of the walls next to the basement of the bus ducts of the negative floors to install the bus duct support
Category +1:
- Execution of mosaic on the floor of the east and west electrical rooms
- Execution of wiring of fire alarm system
Floor +3:
- Execution of fan coil
-5th floor:
- Apply floor protective mortar
- Application of Knauf wall leaf plaster, second layer, second face, RG + 5
- Execution of rock wool
- Execution of support, pipes and cans of switches and sockets
- Execution of wiring (lighting system)
- Execution of wiring (electrical outlet system)
- Execution of support and plumbing of water supply system (galvanized pipe)
Application of elastomeric insulation of water supply system (galvanized pipe)
- Execution of support and plumbing of the fire system (plumbing of fireboxes)
- Execution of mosaic on the floor of the western and eastern electrical rooms
Implementation of waterproofing
Category +6:
- Execution of rock wool
- Execution of mosaic
- Application of Knauf wall leaf plaster, second layer, second face, RG + 6
- Execution of wiring (lighting system)
- Execution of wiring (electrical outlet system)
Installation of return and evacuation air ducts
Implementation of water supply system piping (galvanized pipe)
Application of elastomeric insulation of water supply system (galvanized pipe)
- Execution of steel plumbing
- Execution of sprinkler system pipe
- Execution of medical gas system pipe
Wet floor foaming
Installation of return and evacuation air ducts
-File +8 and above:
- Execution of sewer pipes of +8 floor
- Execution of electrical installations of +8 floor
- Execution of electric pipes for wet spaces in a number of +18 floor offices
- Cementing of wet spaces in a number of +18 floor offices
- Installing switches and sockets in a number of +18 floor offices
- Plastering a number of +18 floor offices
- Completion of cement work in the corridor of the +18 floor, west zone of the +18 floor
- Execution of wall grooves for installing pvc pipes of +18 floor
- Execution of electrical pipe (PVC) floor +18
- Execution of chrome plating of floor +18
- Execution of the stair tread of the +23 floor staircase
- Execution of staircase +23
- Execution of stair tread +24
- Execution of staircase +24
- Execution of staircase +25
- Hardening operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 33%.
- Joinery operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 19 percent.