- 2nd Floor
- Execution of reinforcement of water tank foundation
- Execution of EN5 elevator valcrete
- Execution of water tank decoupling
Water intake of water tank
- Class +2
- Execution of Knauf wall
- Execution of elastomeric insulation of 5-layer pipe system
- Execution of support and plumbing of 5-layer pipe system
- Floor +5:
- Installation of manual dampers and fire channel went
- Execution of support and plumbing of the fire system (plumbing of fireboxes)
- Execution of elastomeric insulation of 5-layer pipe system
- Execution of support and plumbing of 5-layer pipe system
- Execution of elastomeric insulation of water supply system (galvanized pipe)
- Install support and run fresh air ducts
- Execution of supports and cable trays
- Execution of support, pipes and cans of switches and sockets
- Execution of rock wool
- Execution of Knauf wall
- Floor +6:
- Execution of Knauf wall
- Dry space flooring
- Execution of mosaic
- Implementation of medical gas system valve box
- Wall cement work
- Execution of medical gas system pipe
- Implementation of water supply system piping (galvanized pipe)
- Execution of wiring (lighting system)
- Execution of medical gas system control box
- Floor +8:
- Staircase roof painting
- Execution of pipes and cans of switches and sockets
- Execution of cable tray
- Execution of sewer pipes
- Execution of power supply cabling to the floor
- Execution of electrical installations
- Floor +18:
- Execution of horizontal wall post of the inner wall
- Execution of vertical wall posts on the inner wall
- Execution of interior wall foundation wall
- Installing the wall wall post plate
- Execution of stair stones
- Execution of perimeter wall foundation
- Facade installation operation is completed.