- Execution of elastomeric insulation of water supply system of +4 floor and execution of fan coil of +3 and +4 floors.
-Support bricks, pipes and key boxes of +4 and +5 floors and execution of knauf of +5 and +6 floors
- Execution of medical gas system pipe and execution of support and plumbing of fire system +4 floor.
- Execution of control box of medical gas system of +1 floor and execution of wiring of +1 and +3 floors.
- Execution of masonry walls of floors -2, ground floor, +1, +6, +8 and +22 to +25.
- Execution of 4th floor stair stone and execution of stone wool of +3, +4 and +.5 floors
- Execution of pipes and key boxes and sockets and execution of sewer pipes of +6 floor.
- Execution of supports and cable trays of +5 floors and implementation of pipes and supports of sprinkler system of +5 and +6 floors.
- Execution of piping of 5-layer pipe system and implementation of elastomeric insulation of 5-layer pipe system of +4 and +6 floors.
- Execution of supports and cable trays and construction of fresh air ducts and transportation to the workshop and installation of +5 floor.
- The total progress in +1 and +2 classes is about 91%, which is about 92% in the building sector, about 86% in the electrical sector and about 93% in the mechanics sector.
- The total progress in the +3 to +5 classes is about 77%, which is about 83% in the building sector, about 59% in the electrical sector and about 80% in the mechanics sector.
- The facade installation operation is underway and has been carried out up to the 22nd floor.
- Hardening operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 22%.
- Joinery operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 13 percent.