- Carrying out operations related to buildings and facilities in +1 to +6 floors
- Execution of masonry wall of floors +3 to +6 and floors +17 to 23.
- Execution of Knauf wall leaf plaster of + 5 and +6 floors and execution of stone wool of floors +1 to +4
- Execution of wiring (lighting system and electrical outlet system) floors +1 to +4.
- Execution of fresh air ducts back and forth on the +2, +4 and +5 floors and lead beating on the +4 floors.
- Execution of support, pipes and key boxes and sockets of +5 and +6 floors and execution of support and plumbing of water supply system (galvanized pipe) of +5 floors.
- Installation of plate and subframe of +8 floor and execution of sewer pipe of +6 floor.
- Execution of electrical piping and stair wiring of +3 to +5 floors and ground floor to +2.
- The total progress in +1 and +2 classes is about 86%, which is about 84% in the construction sector, about 78% in the electrical sector and about 93% in the mechanics sector.
- The total progress in the +3 to +5 classes is about 73%, which is about 81% in the buildings sector, about 55% in the electrical sector and about 80% in the mechanics sector.
- The facade installation operation is underway and has been carried out up to the 22nd floor.
- Hardening operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 22%.
- Joinery operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 13 percent.