- Carrying out operations related to buildings and facilities in +1 to +6 floors
- Execution of waterproofing of floors 1+ to 3+ and execution of stone floor of floors +1 to +4
- Execution of cementing the stair wall of floors +1 to +6 and execution of Knauf wall of floors +1 to +5
- Execution of round stone, stair wall of floors -6 to ground floor and ground floor to +7
- Execution of support and piping of 5-layer pipes system of +2 to +5 floors
- Execution of someone's wire lighting system and power outlet of +2 and +3 floors
- Execution of support and piping of water supply system of galvanized pipes of +2 to +5 floors
- Execution of key box and socket of +3 to +5 floors and execution of wall posts of +7 to +17 floors
- Execution of masonry wall of floors +7 to +10 and construction of masonry wall of stairs -2 to -7
- The facade installation operation is underway and has been carried out until the 19th floor.
- Operations related to firecrackers in classes -1 and -2 are underway.