- Organizing engineering meetings virtually to review plans
- Pursuing the supply of electricity to the project through the supply contractor and requesting to prepare final supply plans for the project
- Following up with the official forensic expert on the land on the south side of the project
- Organizing weekly HSE coordination meetings with employer managers and contractors present on the site to review workshop safety approvals and notify new approvals
- Prepare reports related to the fight against Covid 19 at the workshop level and submit to the Ministry of Health on a weekly basis
- Organizing workshop meetings to purchase elevators, air conditioners and project engine room equipment
- Following up with the municipality and the green space of the municipality regarding the notifications and doing their cases
- Obtaining a permit for the installation of sewage into municipal sewage in the workshop equipment section
- Installing the facade in the project up to the 10th and 11th floors in different parts
- Buy glass for the project and send it to Namakaran company to prepare the panels and send it to the workshop
- Preparation and approval of workshop plans by the fire fighting consultant
- Dr. Kazemian visited the implementation process of the project from the positive classes
- Review of project plans in accordance with the regulations of the Ministry of Health