January 2019 News
Organize regular weekly engineering meetings with the presence of CEO
HSE Weekly Meetings with Project Agents and assessing the work problems and issues
Conduct regular and continuous weekly meetings with contractors on technical and project issues
Morning meetings in the presence of the CEO and the report of the project managers and contractors to the managing director
Receiving a proceedings of no offense approval from the municipality of Tehran
Follow up of the municipal and fire department file for the transfer of fire and transport sums
Visiting glass factories to buy project window glasses
Visiting aluminum composites factories for the project facade
Participation in the facade commission in the municipality, considering that the previously approved items not allowed entry into the workshop because of the sanctions.
Construction of warehouse for maintenance of friction dampers
Establishment of facade engineering with the presence of facade installation contractors