Implementation of weekly meetings coordinated with the consultant of the employer and contractors
HSE weekly meetings with contractors, site and HSE consultant and project manager
The formation of the commission to buy armature, sheet, bolts
Entry of a fire extinguisher contractor to the project complex and carrying more than 200 tons of product into the workshop and the implementation of the fire extinguisher of the third floor
Sending QC and Resident Supervisor persons to take delicery of the fire extinguisher materials at Shahid Rajaee Port
The study of the method of flooring classes by the consultant and the factors of engineering and project implementation
Visit the Abnoos Project to see flooring
A Comparative Study of the Comparison of the Traditional Flooring and the Use of Polymer Fibers
Study of architectural plans of physiotherapy and radiology wards
Elevating the tower crane 12 tons, 16 tons and 25 tons for the installation of concrete skeletons
Visiting of the project by Tehran University students
Install the projectors on the eighth floor
Drafting a friction dampers purchase contract
Start of the embankment on the negative floor 7
Continued concrete work on ceilings and walls
Installation of -3 floor wallet posts