Establish regular weekly meetings of the employer, consultant and contractor on the technical and executive issues of the project.
HSE unit's regular weekly meetings with contractors
Visit Aransajj Factory by Supreme Steel Design Consultant and Technical Officer
Several technical meetings with the presence of Group 4 Advisor and Technical Project Office on the identification of facade contractors
Preparation of electrical, mechanical and building documents for -9 to -3 floors
Bidding documents for fireproof insulators to cover metal skeleton from -9 to -3 floors
Establishing regular morning coordination meetings between managing director and project implementer
Procurement of documents for purchase friction damper
Investigating tender documents related to electric and mechanical operations and building and winning the Behsara company as a contractor of this class of -9 to -3
Signing the contract for electric and mechanical operations with the Behsara company on March 17, 2018
Opening the tender banners for fireproofing on March 18, 2018 and checking for the winner's announcement
Track purchasing power split 5/6 megawatts
Installing a sample of facade pieces on March 16, 2018
The end of the year ceremony with the presence of all project partner network (consultants - contractors - commodity producers - supervisory board - contractor and employer)