· Continuing the implementation of the hospital's amphitheater and assembly halls on the 1st floor (including the main hall and related classrooms)
· Starting the installation of low-pressure panels in the engine room
· Delivering sealing tapes for soundproofing the air handling rooms
· Continuing the installation of cooling system valves (for the start-up of cooling towers)
· Continuing the installation of roof cooling towers
· Continuing the implementation of the implementation operations on the inpatient floors (including floors 10-11 and 13)
· Continuing the construction of the project's air handling units and reaching a physical progress rate of 50%
· Continuing the installation of project elevators
· Continuing the implementation operations on the 9th floor (air handling rooms)
· Implementing the foundation of fire pumps on the 2nd floor
· Completing the thinning operations of the transformer rooms on the 2nd floor and planning to install two diesel generators
· Delivering two escalators and their initial placement on the ground floor to the first floor and their temporary delivery
· Continue lighting operations for the project's facade on the west side
· Planning to test 1 absorption chiller in the engine room and finish reinforcing its cover
· Temporary delivery of the helipad facade
· Purchase of 5 electrical panels to start the EN13 elevator
· Temporary delivery of the project's facade and planning to settle the account with the abovementioned
· Completion of the heating system of the doctors' building and hot water supply to the relevant floors
· Continue execution of the water tank foundation on the 16th floor
· Delivery of the lift consoles and ceiling columns from Vistatab Company
· Extension of the engineering system contractor contract and notification of the two-year contract to this company
Floor -5:
Construction of the garage door
Central zone tape and mastic
Ground floor:
Painting of the gas station
Floor +10:
Implementation of cable trays
Implementation of facility supports
Installation of return and return air ducts
Floor +11:
Implementation of the foundation of the kunaf wall
Implementation of the plaster sheet of the first face wall Internal Knauf
Executing sewage pipes
Floor +16:
Pipe laying
Executing full mesh walls
Cementing
Earth bonding
Floor +21:
Ceiling frame of the central zone
Executing electrical and wiring plumbing in the central zone
Installing switches and sockets
Floor +22:
Ceramic floor laying
Executing false ceiling panels in corridors
Plastering
Wiring
Executing ceramic body tiles in corridors
Installing flushers
Floor +23:
Cementing corridor walls and services
Electrical plumbing in wet spaces
Floor +24:
Plastering
Executing mosaics
Executing insulating protective mortar
Executing electrical plumbing
Executing sprinkler and galvanized and 5-layer plumbing
Floor +25:
Ceramic floor laying
Physical progress The entire project is 80 percent complete.
The solidification and thinning operations have reached an overall progress of 74 and 54 percent, respectively.