Continuation of internal gas piping operations
Continuing the installation of lighting panels by Payasazeh company
Entry of all the low pressure panels of the engine room and planning to install the panels
Delivery of sound insulation for air-conditioned rooms from Sana Aeeq company
Continue the construction of project air conditioners
Entry of all phase III elevators (28 machines) to the workshop and planning for equipment installation
Carrying out fine work operations of the transformer rooms on the 2nd floor.
Continuation of the operation to remove the defects of the 19+, 20+ and 21+ floors
Continuation of executive operations on the west and east sides of the 17th+ floor
Implementation of operations in the central zones of floors 18+ to 20+
Preparing the south side of the 17th floor for temporary delivery
Completing the construction of escalators in the manufacturer's factory and coordinating the transportation to the workshop and its installation
Continuation of engine house operations
Continuation of executive operations on the 6th floor (parking lot)
Planning to test 1 absorption chiller in the engine room and finish strengthening its cover
Completion of the execution of the helipad facade and planning for its temporary handover
Planning for the implementation of the foundation of water tanks on the 16th floor


6th floor:

Roof painting

Run the light

Implementation of fire alarm cable

Implementation of pipes and cans, switches and sockets

 

2nd floor:

Installation of flange and gasket of steam and water supply system

Installation of steam system valves

Implementation of the drain valve of the collectors

 

Floor 1+:

Demolition for Raz Co

 

Floor 9+:

Implementation of the chassis buried in the concrete floor of the ventilation room

Implementation of the sewage pipeline

 

Floor 10+:

Implementation of leaf plaster on the second side of the perimeter wall

Implementation of Central Zone Valkrit

Implementation of pipes and cans, switches and sockets

Implementation of elastomeric insulation of fresh and outgoing air channels

Installation of air ducts

Implementation of sprinkler system pipes and medical gas and 5-layer pipes

 

Floor 11+:

Subframe installation

 

Floor 17+:

Implementation of full mesh walls

Chrome plating with plaster

Performing mosaic on the balcony floor

Implementation of galvanized piping on the central side

 

Floor 18+:

Ceramic implementation of the central side floor

 

Floor 20+:

Implementation of the chassis of the roof of the central side

 

Floor 21+:

Implementation of electrical operations in the central zone

 

Floor 22+:

Implementation of ceramic floor and body of offices

Implementation of cabling and wiring

Ceramic implementation of the body of the corridors

Wall painting

Implementation of electrical installations

 

Floor 23+:

Installation of flexible pipes and channels

Running the electric pipe

 

Floor 24+:

Grooving the walls (east side)

Implementation of mosaic on the west side

Chinese wall

Full mesh walls

 

Roof:

Implementation of insulation of the roof pool floor

 

The physical progress of the whole project is 79.25%.

The implementation of the facilities has reached a total progress of about 66%.

The implementation of mechanical and electrical facilities has reached a total progress of 69 and 63 percent, respectively.