Continuation of internal gas piping operations
Continuing the installation of lighting panels by Payasazeh company
Entry of all the low pressure panels of the engine room and planning to install the panels
Delivery of sound insulation for air-conditioned rooms from Sana Aeeq company
Continue the construction of project air conditioners
Entry of all phase III elevators (28 machines) to the workshop and planning for equipment installation
Carrying out fine work operations of the transformer rooms on the 2nd floor.
Continuation of the operation to remove the defects of the 19+, 20+ and 21+ floors
Continuation of executive operations on the west and east sides of the 17th+ floor
Implementation of operations in the central zones of floors 18+ to 20+
Preparing the south side of the 17th floor for temporary delivery
Completing the construction of escalators in the manufacturer's factory and coordinating the transportation to the workshop and its installation
Continuation of engine house operations
Continuation of executive operations on the 6th floor (parking lot)
Planning to test 1 absorption chiller in the engine room and finish strengthening its cover
Completion of the execution of the helipad facade and planning for its temporary handover
Planning for the implementation of the foundation of water tanks on the 16th floor
6th floor:
Roof painting
Run the light
Implementation of fire alarm cable
Implementation of pipes and cans, switches and sockets
2nd floor:
Installation of flange and gasket of steam and water supply system
Installation of steam system valves
Implementation of the drain valve of the collectors
Floor 1+:
Demolition for Raz Co
Floor 9+:
Implementation of the chassis buried in the concrete floor of the ventilation room
Implementation of the sewage pipeline
Floor 10+:
Implementation of leaf plaster on the second side of the perimeter wall
Implementation of Central Zone Valkrit
Implementation of pipes and cans, switches and sockets
Implementation of elastomeric insulation of fresh and outgoing air channels
Installation of air ducts
Implementation of sprinkler system pipes and medical gas and 5-layer pipes
Floor 11+:
Subframe installation
Floor 17+:
Implementation of full mesh walls
Chrome plating with plaster
Performing mosaic on the balcony floor
Implementation of galvanized piping on the central side
Floor 18+:
Ceramic implementation of the central side floor
Floor 20+:
Implementation of the chassis of the roof of the central side
Floor 21+:
Implementation of electrical operations in the central zone
Floor 22+:
Implementation of ceramic floor and body of offices
Implementation of cabling and wiring
Ceramic implementation of the body of the corridors
Wall painting
Implementation of electrical installations
Floor 23+:
Installation of flexible pipes and channels
Running the electric pipe
Floor 24+:
Grooving the walls (east side)
Implementation of mosaic on the west side
Chinese wall
Full mesh walls
Roof:
Implementation of insulation of the roof pool floor
The physical progress of the whole project is 79.25%.
The implementation of the facilities has reached a total progress of about 66%.
The implementation of mechanical and electrical facilities has reached a total progress of 69 and 63 percent, respectively.