Continuing the operation of the amphitheater and meeting halls of the hospital on the 1st floor
Completion of the construction of all low pressure panels in the engine room and planning for the panels to enter the project
Sending a letter to Sana Aeeq company to deliver the last part of the sound insulation of the air-conditioned rooms according to the verification of the project sizes.
Continuing the installation of cooling system faucets (to set up cooling towers)
Continue installing roof cooling towers
Installing the electrical panel of one of the roof chillers to the workshop
Setting up one of the rooftop compression chillers
Executive operations in the inpatient floors (including floors 10-11 and 13)
Continue the construction of project air conditioners
Executive operations of the 9th floor+ (air conditioning rooms)
Implementation of the foundation of fire pumps on the 2nd floor
Complete disassembly of the 25 ton tower crane and its removal from the workshop
Renovation of the facade (Hold Tower)
Continuation of the operations to remove the defects of the 19+, 20+ and 21+ floors
Start of operations on the 17th+ floor (Yal C)
Continuing the assembling operation of escalators in the manufacturer's factory and coordinating the transportation to the workshop and its installation
Continuing to complete the engine room with the priority of electrical operations
Continuation of the implementation of the completion of the 6th floor (parking)
Conducting tenders and receiving tender envelopes for the electrical panels of the floors of Phase I
Continuation of lighting operations on the west side of the project
Continue the operation of the helipad view
Initial negotiation with Surin Italy company to continue concreting the roof of the radiotherapy bunker with a 25-ton tower crane.
6th floor:
Implementation of support and anti-rust sprinkler pipe
2nd floor:
Installation of intermediate parts
Soft water pipeline disassembly
Full welding of engine house pipelines and supports and implementation of soft water pipeline
Execution of false work of room columns and chassis and floor mesh and concreting of trans floor
Building a wall and installing wallpaper and cementing the wall
Implementation of the plan to strengthen the floor of the 2nd floor
Floor 17+:
Performing wall painting and installing lights
Implementation of fire piping
Floor 21+:
Continuing the painting of the ceiling of the offices and the flooring of the central side
Floor 22+:
Continue the execution of the false ceiling panel and ceramic floor and central side flooring
Implementation of cabling and wiring
Floor 25+:
Continuing the installation of the sleeping floor and the execution of the ceramic floor of the dry space
Implementation of public service sewage piping
Roof:
Modifying and completing facade substructure, cutting work, execution of facade substructure, installation of facade composites, collection of 25 ton tower
The physical progress of the whole project is 78.99%.
Hard work and thin work operations have reached 70% and 51% overall progress, respectively.