- Operations related to buildings and facilities in the +1 to +6 floors are underway.
- The total progress in the +1 and +2 classes is about 90%, which is about 91% in the buildings sector, about 70% in the electrical sector and about 98% in the mechanics sector.
- The total progress in the +3 to +5 classes is about 66%, which is about 75% in the buildings sector, about 38% in the electrical sector and about 65% in the mechanics sector.
- Operations related to the buildings of the central zone from floors +7 to +16 are underway, and operations related to the walling of floors +16 to +19 are underway.
- The installation of the facade is underway and has been carried out up to the 18th floor, and the progress of the total facade of the project is about 67%, of which the unit view is about 74% and the installation of the stick facade is about 60%.
- Operations related to firecrackers in classes -1 and -2 are underway and the overall progress is 92%.
- Execution of ironing of 57 elevators and execution of escalator infrastructure and purchase of hardware needed for execution of elevator
- Supply and construction of building chillers, supply and construction of building air conditioners +1 to +6 floors and supply of facade lighting equipment
- Execution of the roof of the entrance and exit ramps of the hospital, execution of the climber base, execution of the stairs of the whole floors, execution of the installation secrets of the whole building and execution of the Basdak system for electricity supply.