Hold regular morning meetings to report to the Director of the project
Holding engineering meetings with consultant and employer agents to review executive issues
Organize meetings of the employer, consultant and contractor to discuss workshop issues
Installation of the majestic walls of the operating room and visits by the esteemed director of the installation of five manufacturing companies
Visit the Aspitex Exhibition in coordination with the CEO of the company and the pillars of the project
Establish trading commissions for the purchase of workshop equipment such as galvanized sheets, iron and round bars.
Contract for radiotherapy bunker announced to Surin Ista Bana Co.
Bidding for facial polishers and contractor selection for construction and installation
Perform hard work, and work on the negative floors
Perform partitioning, flooring, electrical and mechanical operations on the ground floor up to the fifth floor and continue installing facade panels
Visit of the Students of Tehran University of Engineering and West Tehran Islamic Azad University from the project
Installation of main and side pillars and beams of helipad
Workshop electrical contractor selection