Organize weekly engineering meetings with project partners, employers, consultants and contractors
Organize morning meetings with project managers and brief the respected CEO
Conduct regular HSE meetings and review ongoing work and project barriers and risks
Tracking project electricity purchase
Meeting with an official justice expert on project overland south side of the project
Follow-up and meeting with the Office of Municipal Partnerships to obtain a license for the construction of the 26th floor
Official Courts of Justice at Rates to Determine share of the Municipal Participation Bureau
Multiple technical meetings with the engineering system supervisor regarding the installation of dampers
Install friction dampers on project floors
Installation of Dry Wall and Cable & Pipe Supports and Carpet Mosaic
Implementation of mechanical and electrical installations of the first and second floors by the contractor
Anti Fire contract with Abtek & Beta companies 9th to 25th floors
Installation of helipad columns in the final floors
Submission of tender documents for purchase of radiation therapy bunkers and climers
Purchase sewage treatment equipment and prepare it for shipment to the workshop
Implementation of acoustic facade on west side and installation of facades and supports of facades in south and east sides
Visiting anti-fire material by QC unit prior to shipment to workshop
Visiting facade materials by engineering and consulting unit in Turkey