• Continue to install the metal skeleton in zones 3A 3B 4A 4B at different levels
• Run the ceiling at different levels of zones 3A 3B 4A 4B
• Removing a 100-ton crane from the inside and replacing the 35-tonne and 50-ton crane on the western side to speed up the installation of the metal skeleton
• Elevation of 12 tones and 25 tones to maintain skeletons at higher levels
• Performing the night shift on the implementation of the metal structure from mid-May due to air assistance
• Establishing meetings with project partners on the timetable and method of implementation and the process of project continuation
• Make necessary project purchases including armature, steel plate, bolts and nuts in different sizes
• Track the purchase of power and gas splits for the project