• Continuing internal gas piping operations and conducting pipe welding tests under the supervision of the engineering system supervisor and continuing the operational operations
of expansion loops
• Continuing the installation of parts on the engine room ducts
• Planning for the entry of cooling tower packing
• Continuing the operational operations on the hospital floors (including floors 10-11 and 13)
• Continuing the construction of the project's air conditioners and reaching a progress percentage of about 72%
• Continuing the installation of the project's elevators and planning for the reopening of the passenger elevators
• Continuing the operational operations of the engine room
• Continuing the construction of electrical panels for the first phase of operation floors and delivering 90 electrical panels
• Continuing the operational operations of floors 1+ to 3+
• Continuing the assembly operations of the project's air conditioners in the workshop
• Completing the operational operations of installing VRF on the eastern ridge 17+
• Installing three monorail trolley devices
• Starting the installation of 2 plate exchangers on the 9+ floor
• Notifying the contracts for floors 8+, 16 and the roof
• Starting the installation of waste disposal devices on the floor 2-
• Continue construction of the remaining 33 air conditioners
• Notify the contract for the purchase of 80 automatic doors in the first phase
• Notify the contract for the project's insulated panels to TTM Company
• Notify the contract for VRFs on the 1st floor
• Notify the contract for 1362 plywood doors
• Negotiate with Maksh Dehsh Company regarding equipment
Floor 1+:
Implementation of wall posts in the central zone
Improvement of pipe insulation
Improvement of cabling
Installation of support and access pipes for doors
Floor 7+:
Improvement of sewage piping
Floor 9+:
Installation of support and full welding
Construction of chassis and placement of the air handling unit
Improvement of galvanization
Improvement of chassis for gas riser
Floor 10+:
Improvement of roof foundation
Improvement of duct box insulation
Improvement of ceramic tiles for the walls of the bathrooms
Completion and closing of the riser's knauf wall
Floor 11+:
Improvement of fire alarm cabling
Installation of wall supports and pipes
Implementation of bathroom floor insulation
Implementation of Knauf riser walls
Floor 18+:
Implementation of cabling and end caps for elevator panels
Floor 23+:
Installation of switches and sockets
Implementation of plastering
Installation of window flashing
Installation of bathroom panels
Floor 24+:
Implementation of ceramic wall and floor tiles in spaces
Implementation of painting of the eastern zone wall
Floor 25+:
Installation of linear lights in elevator lobbies of all three zones
Implementation of mosaic and ceramic floor tiles
Installation of interior doors for bathrooms
The physical progress of the entire project is 84.24 percent.
The overall progress of the stiffening and thinning operations has reached 83 and 67 percent, respectively.