July 2025 News

July 2025 News

• Arrival of remaining parts of the engine room ducts to the workshop and start of parts installation
• Continue construction of the project air conditioners and reach a progress percentage of about 60%
• Temporary delivery of the 22nd floor and start of fixing the related defects
• Continue installation of the project elevators and entry
• Continue execution operations of the 9th floor (air conditioner rooms)
• Planning to install two diesel generators on the 2nd floor and meetings for ventilation and exhaust paths of the generators
• Continue execution operations of the 6th floor (parking lot)
• Completion of lighting operations of the project facade on the west side and the entrance windows of the facade recesses and planning to light the upper 1/3 of the tower
• Purchase and installation of all water tank valves on the 16th floor
• Continue construction of electrical panels for the first phase of operation floors and delivery of 60 electrical panels
• Arrival of 8 sets of steam chiller valves from ARI Company
• Continue installation of air conditioners in the air conditioner rooms on the 1st floor and the 1st floor
• Continue GPON infrastructure operations on floors 11-10-7 and -1 and ground floor
• Completion of helipad scaffolding to begin lighting operations
• Arrival of all internal and external VRF units of the eastern ridge of the 17th floor+
• Follow-up on the construction of monorail climb baskets
• Completion of concreting of the roof of radiotherapy bunkers
• Coordination with Aryabnis Company to arrive at the first shipment of cooling tower packings
• Notification of the contract to purchase two plate heat exchangers from Taha Ghaleb Toos Company
• Coordination with the VRF installation contractor of the eastern ridge of the 17th floor+ to purchase materials and start installation
• Coordination with Arman Tajhiz Company to arrive at two waste disposal devices
• Review of the request of Rifle Company to adjust the contract prices
• Planning for the purchase of automatic doors, phase 1
• Planning for the purchase of wooden doors, phase 1

Floor 6-:
Installation of ducts

Painting of signs

Floor 1+:
Chrome plating of the central zone wall
Installation of hatches

Floor 7+:
Execution of corridor foundation
Execution of fire and smoke barriers for electrical elements
Execution of sewage pipeline

Floor 9+:
Installation of utility supports and trays
Execution of fit-up, welding and line support

Floor 10+:
Execution of foundation and panel installation
Execution of fire and smoke barriers
Execution of central zone wall tiling
Execution of ceramic wall tiling
Execution of central zone flooring
Execution of network cabling
Installation of isolated panel support

Floor 13+:
Execution of ceiling foundation and wiring box
Execution of first side panel
Execution of wall foundation
Execution of sprinkler lines, galvanized and 5 layers and firebox

Floor 16+:
Execution of cabling for facade lighting

Floor 17+:
Execution of fire and smoke barriers for main riser
Execution of wall tiling
Execution of plumbing Sprinkler
Installation of ducts
Execution of underlayment

Floor 18+:
Installation of supports and trays for elevator panels

Floor 19+:
Installation of public service frames

Floor 20+:
Execution of network cabling

Floor 22+:
Supplementary operations for temporary delivery

Floor 25+:
Execution of pipe insulation
Execution of floor and wall ceramics
Execution of ceiling panels for corridor and central zone

The physical progress of the entire project is 83.03 percent.
The implementation of mechanical and electrical installations has reached an overall progress of 76 and 71 percent, respectively.