• Temporary handover of the executive operations of the large amphitheater hall and lobby on floor +1
• Installation of low-voltage electrical panels of the engine room and coordination with Lenazd Company for the entry of bus ducts into the upper part of the panels
• Continuation of executive operations on the hospital floors (including floors 10-11 and 13)
• Continuation of the construction of the project's air conditioners and reaching a progress percentage of about 60%
• Temporary handover of floor +22
• Continuation of the installation of the project's elevators
• Continuation of the executive operations of floor +9 (air conditioner rooms)
• Planning for the installation of two diesel generators on floor -2 and meetings for ventilation and exhaust paths of the generators
• Fixing the defects of floor +21 and handing over to the operators
• Continuation of the executive operations of the central zones of floors +18 to +20
• Continuation of the executive operations of the engine room
• Continuation of the executive operations of floor -6 (parking lot)
• Continuation of the lighting operations of the project's facade on the west side
• Continuation of the construction of the electrical panels First phase of operation and delivery of 20 electrical panels
• Start of executive operations on floors 1+ to 3+
• Installation of air conditioners in the air conditioner room on floor 1+ and floor -1
• Start and continue GPON infrastructure operations
• Finish construction of the engine room's duct space and planning for transporting equipment
• Start of executive operations on the helipad lighting
• Signing a purchase contract for the VRF of the eastern slope of floor +17
• Signing a purchase contract for the roof engine room equipment from Pakman Company
• Signing a purchase contract for monorail climbers
• Start of executive operations for concreting the remaining radiotherapy bunker on floor -9
• Meeting with Aryabnez Company to send the cooling tower packing
Floor 1+:
Installation of chassis and placement of air conditioners
Floor 7+:
Implementation of ceramic body of wet spaces
Installation of electrical and cabling supports and piping
Implementation of sewage pipeline
Floor 9+:
Installation of utility supports
Implementation of pipes Steel coating
Floor 10+:
Installation of wall ceramic tiles
Installation of fire and smoke barriers
Floor 17+:
Installation of east side service grooves
Floor 18+:
Installation of central side lights
Installation of ceiling steel pipes and support installation
Floor 21+:
Installation of central side waste collection room ceramic tiles
Installation of central service zone ceramic tiles
Floor 22+:
Installation of lights, switches and sockets
Installation of central side floor ceramic tiles
Floor 25+:
Installation of sprinkler piping
Installation of wall ceramic tiles
Installation of water supply pipe insulation
Installation of central side roof infrastructure
The physical progress of the entire project is 82.57 percent.
The overall progress of the facilities has reached about 73 percent.
The implementation of mechanical and electrical installations has reached an overall progress of 75 and 70 percent, respectively.