February 2025 News

February 2025 News

• Continuing internal gas piping operations and conducting pipe welding tests under the supervision of the engineering system supervisor
• Continuing the implementation of the hospital's amphitheater and assembly halls on the 1st floor (including the main hall and related classrooms)
• Planning to start the second compression chiller on the roof
• Continuing the implementation of implementation operations on the inpatient floors (including floors 10-11 and 13)
• Continuing the installation of project elevators
• Continuing the implementation operations on the 9th floor (air conditioning rooms)
• Planning to install two diesel generators on the 2nd floor
• Continuing the implementation operations on the west and east sides of the 17th floor
• Continuing the implementation of the implementation operations of the central zones of floors 18+ to 20+
• Continuing the implementation operations of the engine room
• Planning to test 1 absorption chiller in the engine room and completing the reinforcement of the second chiller cover
• Continuing the construction of electrical panels for the first phase of operation

Floor 6-:
Execution of joints Earth

Floor 2-:
Implementation of engine room supports
Full welding of engine room pipelines
Implementation of engine room plumbing
Implementation of ironwork

Floor 1-:
Implementation of the substructure of the kenaf wall
Implementation of cement work
Implementation of electrical plumbing

Ground floor:
Implementation of porcelain and full mesh walls
Implementation of wall posts
Implementation of cement work

Floor 7+:
Installation of floor sockets for sleeping

Floor 9+:
Implementation of wall posts

Floor 13+:
Implementation of riser substructure

Floor 22+:
Implementation of corridor panels
Implementation of floor ceramics
Implementation around the window
Implementation of floor ceramics on the central side

Floor 23+:
Installation of linear vents on the central side
Implementation of floor ceramics in the wet area
Lobby wiring
Implementation of false ceiling chassis

Floor 24+:
Installation of ducts connecting to the fan duct Coil
Execution of ceramic body and floor
Supporting the central side
Installation of connection channels to the riser
Execution of cabling
Installation of supports and piping in the central zone

Floor 25+:
Execution of galvanized drainage piping
Execution of electrical piping
Installation of side supports
Canning of wet spaces (lobby and services)
Execution of slope of the central side service

The physical progress of the entire project is 82.18%.
The overall progress of the stiffening and thinning operations has reached 80 and 59 percent, respectively.