• Continuing internal gas piping operations and conducting pipe welding tests under the supervision of the engineering system supervisor
• Planning for the commissioning of low-pressure electrical panels in the engine room
• Continuing executive operations on the hospital floors (including floors 10-11 and 13)
• Continuing the construction of the project's air conditioners and reaching a physical progress percentage of 55%
• Continuing the installation of project elevators
• Continuing the execution of the foundation of fire pumps on the -2 floor
• Temporary handover of the 21+ floor and forming the relevant commission
• Continuing the execution of executive operations in the central zones of floors 18+ to 20+
• Utilizing the southern side of the 17+ floor and handing it over to its owners
• Continuing the execution of the engine room executive operations
• Continuing the execution of the -6 floor (parking lot)
• Continuing the lighting operations of the project's facade on the west side
• Completing the foundation of the water tanks on the 16+ floor and assembling them
• Continuing the construction of the electrical panels on the floors of the first phase of operation
• Announcing the desired plan Helipad lighting to RGE and obtaining its price
• Arranging the purchase contract for the remaining steam valves of the engine room
• Obtaining the proposal and price for the executive operations of floors 1 to 3 from Payasazeh Company
• Transferring the air conditioner to the air conditioner room on floor 1+
• Negotiating with the CEO of Rifle Company and coordinating the assembly of air conditioners
• Solving the weak current issue of the project and notifying it to Payasazeh Company to start and continue GPON infrastructure operations
• Planning for the installation of the escalator to access the amphitheater
Floor 1+:
Implementation of the Knauf wall panel
Implementation of cabling
Construction and installation of the channel
Implementation of electrical piping
Implementation of the sewage pipeline
Installation of the plenum box of the amphitheater linear valve
Implementation of the cables of the air conditioner room and escalator
Implementation of the fiber optic cable
Floor 7+:
Implementation of the ceiling canister
Floor 10+:
Implementation of the Knauf wall panel and tape and Putty
Rock wool installation
Concrete flooring installation
Pipe and duct insulation installation
Medical gas pipeline installation
Pipe and wiring installation
Floor 11+:
West side Knauf wall panel installation
Firebox and sprinkler pipeline installation and galvanized pipe installation
Fan coil installation
Knauf wall type and putty installation and Knauf wall panel installation
Full core mesh installation
Joint support installation
Electrical plumbing installation and cable tray installation
Channel insulation installation
Floor 17+:
Sewerage pipeline installation
Wall post installation
Mosaic installation
Full mesh installation
Wall installation
Floor 20+:
Central side ceiling painting
Floor 25+:
Cementing installation
Channel insulation installation
Central core cementing installation
Protective mortar installation
Sprinkler pipeline implementation
Galvanized and 5-layer piping implementation
Electrical piping implementation
The physical progress of the entire project is 82 percent.
The implementation of the facilities has reached an overall progress of about 72 percent.
The implementation of the mechanical and electrical facilities has reached an overall progress of 74 and 69 percent, respectively.