April 2022 News

1 June 22 Print

April 2022 News

April 2022 News

Negative and ground floors:
- Ceramic execution of floors -4 and -5
- Execution of corrugation for the implementation of sewer pipes in the 1st floor
- Execution of sewer pipes (area number 1) floor-1
- Execution of sprinkler piping, 4th floor
- Execution of pipes and sockets of the 4th floor socket switch

Engine room floor:
- Construction of underhead saddles for cooling system piping
- Execution of cooling system pipelines on supports
- Installing the flange and gasket of the steam system
- Initial installation of steam system piping supports
- Execution of steam system pipelines on supports
- Initial installation of soft water piping supports
- Execution of sewer pipeline support
- Execution of stainless steel expansion chassis
- Execution of stainless steel steam pipeline
- Destroying a part of the fire engine in order to implement the main engine room supports
- Fit up the main engine room pipeline on the ground
- Stainless implementation of the main engine room supports
- Full welding of the main engine room supports

Floor +2:
- Wiring (UPS system)
- Execution of wiring (electrical system)

Floor +5:
- Wiring implementation (lighting system)
- Execution of UPS system wiring))
- Execution of wiring (audio system)
- Execution of wiring (fan coil system)

Floor +7:
- Implementation of water supply system piping (galvanized pipe)
- Execution of steel piping
- Execution of medical gas system pipe
- Execution of cable tray
- Execution of pipes and cans of switches and sockets
- Execution of Knauf wall substructure
- Execution of rock wool
- Execution of gypsum wall leaf plaster

- The physical progress of the whole project is 66%.
- Implementation of facilities related to parking lots, clinics and hospitals is underway and the overall progress has reached about 35%.
- The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached an overall progress of 39%.
- The implementation of electrical installations related to parking lots, clinics and hospitals has reached an overall progress of 31%.