January 2022 News

1 March 22 Print

January 2022 News

January 2022 News

- Negative and ground floors:
- Execution of stair treads on floors -1 and -3
- Execution of elevator wall post EN10 ground floor

- Class +1:
- Execution of wiring (electrical system)
- Ceramic execution
- Execution of flooring of western and eastern electrical rooms
- Execution of white cement in the western and eastern electrical rooms
- Execution of mesh and adhesive Valkyrie of the western and eastern electrical rooms
- Execution of wallcrete wall of western and eastern electrical room
- Execution of UPS + 1 wiring
- Wiring implementation (lighting system)

- Floor +4:
- Execution of wiring (fire alarm system)
- Execution of wiring (electrical system)
- Wiring implementation (lighting system)

- Floor +5:
- Execution of Knauf wall plaster, first layer, first face, FM + 5
- Execution of UPS system wiring + 5))
- Execution of wiring (fan coil system)
- Execution of elastometric insulation of steel pipe
- Execution of wiring (audio system)

- Floor +6:
- Execution of wiring (audio system)

- Floor +7:
- Execution of joint support
- Execution of pipes and cans of switches and sockets

- Floor +17:
- Installing the wall wall post plate
- Execution of interior wall foundation wall
- Execution of perimeter wall masonry
- Execution of vertical wall posts on the inner wall
- Execution of horizontal wall post of the inner wall
- Install plate wall post perimeter wall
- Execution of vertical wall posts on the surrounding wall
- Execution of horizontal post wall of the surrounding wall

- Class +19:
- Execution of power pipe on the dry space wall of office B1 to B10
- Execution of wet space sewage piping in office c4 c5 c6
- Execution of sewage piping of wet spaces of A1 to A9 offices
- Execution of sewage piping in wet spaces of offices C1, C2, C3
- Execution of electrical pipes in wet spaces of offices A1, A2, A3
- Installation of wet spaces in offices C1, C2, C3
Office plastering B2 to B5

- Hardening operations related to parking lots, clinics and hospitals in progress And has reached an overall progress of about 38%.
- Joinery operations related to parking lots, clinics and hospitals in progress And has reached an overall progress of about 24 percent.