May 2021 News

2 July 21 Print

May 2021 News

May 2021 News

- Floors +1 to +4
Execution of valve of medical gas system, cement facade of +1 floor
Execution of fan coil, installation of support and execution of fresh and departure air ducts, construction of return air ducts and evacuation and transportation to the workshop, installation of manual dampers and fire ducts, elastomeric insulation of return air ducts and evacuation of +2 floor
Execution of waterproofing floor +3
Execution of support, pipes and cans of switches and sockets, installation of support and execution of fresh air ducts, installation of support and execution of return air ducts and evacuation of +4 floor
- Floor +5:
Execution of support, pipes and cans of switches and sockets, implementation of supports and cable trays, installation of support and implementation of fresh air ducts, installation of elastomeric insulation of fresh air ducts, installation of support and implementation of return and evacuation air ducts, implementation of support And fire system piping (firebox piping), implementation of medical gas system piping
- Floor +6:
Execution of elastomeric insulation of fresh air duct, execution of pipes and cans of switches and sockets, execution of cable trays, execution of sewer pipes, installation of fresh air ducts, elastomeric insulation of return air ducts and discharge, installation of return air ducts and discharge, Water supply system piping (galvanized pipe), 5-layer pipe system piping, 5-layer elastomeric insulation system, Sprinkler system pipe, medical gas system pipe, perimeter hemp wall substructure, rock wool, Execution of fire system piping (firebox piping)
- Floor +8:
Execution of wall post, execution of masonry wall, execution of tiles, execution of ceramics, dry flooring, installation of door frame, execution of pipes and boxes of switches and sockets, installation of subframe, installation of wall post plate, installation of subframe plate
- The facade installation operation is underway and has been completed up to the 25th floor, and the overall progress of the project facade has reached about 83%.